Slide 9

Gantt Planning

Task Timeline
Acquire offers for installation of telemetry equipment T-30
Installation of telemetry equipment T
Demo period T+28
Demo period end, write paper T+42
Present paper and projections to administration T+42
Draft 2 year plan T+72
Installation in 90%+ of classrooms and lecture halls T+1897